Holt Water accepting bids for new well

Holt Water Well No. 3 was built in the Holt Industrial Park in 2006.

HOLT, Fla., June 23, 2026—Holt Water Works Inc. is accepting bids for a new water well to be built on Calliver Cut Off.

Those interested are invited to submit a sealed bid for construction of Potable Water Well No. 4 to the Holt Water office by 9 a.m. July 23.

Bids will be opened and read aloud at that time.


Related: Holt Water to receive $4 million for new well, tower


The project consists of construction of a 500 gpm potable water well and associated water treatment plant building, including related site work.

A pre-bid conference will be held July 7 at 9 a.m. at the Holt Water office.

Holt Water reserves the right to accept or reject any or all bids, to waive any bid informalities and to re-advertise for bids if it’s determined to be in its best interest to do so.

Bid documents may be examined at two locations:

  • Municipal Engineering Services Inc., 8574 Turkey Bluff Road, Navarre, FL 32544
  • Holt Water Works office, 4618 Johnson St., Holt, FL 32564

Any questions should be directed to Dale E. Long, Municipal Engineering Services engineer, at dlong@mesi-fl.com or 850-428-0285.

Copies of bid documents may be obtained from Long. Cost is $50 for each set. Electronic documents in .pdf format are available upon request. Cost is $10 for a CD or free via email.

Bid documents are non-refundable.

Leave a comment